Objective
To generate 10% of electricity from on site renewable source.
Solution
After a rigorous tendering process South Facing were selected to install the roof mounted PV system. South Facing were also able to advise the client enabling them maximise their return on investment
Structural surveys revealed the most cost effective mechanical fixing solution
System details
Modules – 690x poly crystalline modules
Inverters – Fronius IG series
Total System Output 115kWp
Result
Despite weather delays the installation of the solar PV roof was completed and commissioned on time and with out interruption to the build programme